Okay, thanks, Paula. I'll begin today with our most frequently asked question, what's the latest in New York and Vermont? Starting in Vermont, at the end of October, the Atomic Safety and Licensing Board denied a late filed contention on hard-to-access electric cables, finding that reopening the case was not likely to lead to a different outcome. The petitioner, the New England Coalition, appealed that decision to the Nuclear Regulatory Commission. In parallel, we continued to supply the NRC staff information on related issues to assure the safety valuation report remains complete as time continues to pass. And as you know, we are over five years since our original filing. Regardless, once the expected supplement to that safety valuation report is issued, we're expecting a positive decision from the NRC on VY [Vermont Yankee] license renewal application. Importantly, NRC regulations allow for the commission to issue the license during a pending appeal. We are committed to maintaining open and timely communications in Vermont, however great the challenge is for gaining public support in disproving the negative put in the public's mind that the age of the plant is determinant of its condition. That is essentially the position Governor Shumlin took last month when he said, "It was designed to be shut down in 2012, and that 40 years is up in 2012." He went on to say, "It's old, it's tired, and it should be retired." In fact, he has encouraged New York to take the same position. States or governors are certainly free to voice their opinions, but the NRC, which has jurisdiction on these matters, must deal with the facts. The truth is, what those in the industry already know to be true, that the 40-year license was based on the expected economic life, not the physical life, the nuclear plants were designed for. Recognizing this fact, the NRC set two principals in reviewing license renewal applications. First, that all operating plans provide and maintain an acceptable level of safety; and secondly, each plant's licensing basis is required to be maintained during the renewal term in the same manner and to the same extent as during the original licensing term. To that point, with the constant replacement of equipment and design upgrades, most of the 1970s vintage plants are in excellent operating condition, and Vermont Yankee's operating records certainly supports that fact. For example, during the first 30 years of its life, Vermont Yankee's average capacity factor was below 78% and it never had a breaker-to-breaker run. Over the last five years, the capacity factor has been above 94% and it has had two breaker-to-breaker runs. In fact, Vermont Yankee has been evaluated in the excellent category as compared to its peers. Efforts also continue to secure a new power purchase agreement with the Vermont Utilities. Negotiations had been ongoing for some time now, and we have made progress toward reaching agreement on key terms and conditions that would provide citizens of Vermont continued access to clean and affordable power. However, while we would certainly prefer to sell power in state, that is not a necessary condition, of course. We expect to have clarity by around the middle of 2011 on all the open issues we are pursuing, including but not limited to securing a PPA with the local utilities. Importance of Vermont Yankee's continued operations to Vermont was highlighted in a presentation given last month by ISO-New England to a Vermont incentive committee. The system operators' assessment of reliability of the Vermont electric system found what you would expect; that with that amount without Vermont Yankee, existing state reliability risks increase. ISO-New England studies on the performance and costs of transmission solution alternatives to VY are expected in first half of 2011. But not only would reliability likely deteriorate, studies have shown power rates would also rise as supply is reduced. To that point, on January 26, 2011, IBM, the major employer in Vermont, said, "It takes about $35 million a year in power to power its Vermont facility, and the company estimates those costs will go up by 25% if Vermont Yankee goes offline." And in an open letter to Governor Shumlin on February 3, 2011, community leaders representing industry, labor and energy stakeholders expressed concern that the window of opportunity was closing to allow the Public Service Board to complete its docket of Vermont Yankee's continued operations beyond 2012 and emphasized the serious economic consequences for Vermont if the plant is not allowed to operate under a renewed license. One final note on Vermont Yankee, in early of November, we announced the process to explore potential sale of plant. The confidential nature of the process does not allow me to provide any updates today, but all our actions remain consistent with the objectives of keeping the plant open and meeting stakeholder needs. For the pessimists, and I know there may be a lot of you out there on this issue, one thing you should know is, and it may not have been well, but over the last few years, VY's earnings contribution to Entergy at best has simply covered its fully allocated overhead. Some of that is fixed and some of that is variable. Turning to New York. On December 3, a significant milestone was achieved when NRC issued the final supplemental environmental impact statement. In short, the NRC staff concluded that there were no environmental impacts that would preclude another 20 years of operation for new deployed units. The ASLB will now hold hearings on these new contentions which begin at the end of this year or early next. Also in December, the Administrative Law Judges with the New York Department of Environmental Conservation issued a ruling and schedule in the water quality certification and the State Pollutant Discharge Elimination System or SPDES water permit proceedings. The schedule is set for hearing to begin June 14 before the ALJs on a number of issues, including the threshold issue, regarding whether Entergy could even obtain air permits necessary to build and operate cooling towers in Indian Point, given the Air Quality's [National Ambient Air Quality Standards] non-attainment status in the area. Related issues in force include the effectiveness of our proposed best technology available alternative, Wedgewire screens. A decision by the ALJs on the issues to be tried starting this summer could be referred to the commissioner of the New York Department of Environmental Conservation by the end of this year or early next. As you know, on January 18, President Obama issued an executive order based upon the principles that the regulatory system, "must protect public health, welfare, safety and our environment while promoting economic growth, innovation, competitiveness and job creation; and must promote predictability and reduce uncertainty; and must identify and use the best, most innovative and least burdensome tools for achieving regulatory." He went on to say, "A government-wide review of the rules already on the books to remove outdated regulations and stifle job creation and make our economy less competitive." The executive order was issued to make clear, "that this is the operating principle of our government." Certainly, the cooling tower versus Wedgewire screens matter at Indian Point and similar cooling water intake issues around the nation would seem to be a good opportunity to meet the President's stating operating principle for government as EPA moves toward issuing new intake structure rules. Then on January 27, Chairman Fred Upton of the House Energy and Commerce Committee called on the NRC for greater transparency and certainty in the license renewal process. He stated that, "Gone are the days of reasonable expectation for a stable and predictable regulatory process, and that this uncertainty and lack of transparency in the process is needlessly putting plants and thousands of jobs at risk." In particular, Chairman Upton sited the applications for Pilgrim and Vermont Yankee, saying, "Today marks an unfortunate milestone for the Nuclear Regulatory Commission as the timeline for the reactor renewal process has now doubled without explanation, eclipsing 60 months with no end in sight." And just yesterday, on the Senate side, in their own letter to the NRC, Senators Inhofe and Vitter referenced Chairman Upton's letter as well as President Obama's Executive Order, questioning the extended timeframe to review license renewal applications for plants in some areas of the country and the need to protect the rights of the applicants, as well as the public or local citizens in the process. They requested responses to their specific questions by February 24, as well as such things as e-mails and phone logs supporting the activity to date. The mounting press rates on these issues seem to be driven by the fact that federal government has cleared jurisdiction on these issues and Congress is questioning whether that is being exercised as intended. In any event, we're hopeful that this increased attention will bring expedited resolution. Moving on to the utility. When we announced the [indiscernible] spin-off in 2007, a lot of people questioned who would want the utility stock when EWC or Enexus at the time, was so attractive. We answered those questions with our belief that the utility was still a work in progress or unfinished business. Part of our strategy back in 1998, when we changed management, was to make it the premier utility in America. But between dealing with operational issues and the cost to rebuild the system after five of the six of the largest hurricanes in the history of the company and the fallout from numerous System Agreement disputes, we have never achieved the full potential that we had envisioned for the utility. But today, it is a lot closer than it was then, and it's a lot closer that some may have noticed. In October of last year, we raised our long-term net income outlook for the Utility segment to 6% to 8% compound average growth through 2014 from the previous 5% to 6%, one of the fastest-growing utilities, if not the fastest in the country. As you know, we have secured recovery of $2.4 billion of storm costs and established cash reserves of nearly $330 million today, something that you wouldn't have imagined even possible five years ago. One of the two key drivers of the industry-leading outlook is earning our allowed ROEs in all jurisdictions, particularly Arkansas and Texas. The rate actions approved in both states in 2010 were constructive, but there's still more work to be done. Looking ahead, timely recovery of increasing capacity costs is expected to be a significant risk, affecting Entergy Texas' future financial performance. To that end, we are working with our state legislators on legislation to be introduced in the near future that would give the PUCT explicit authority to implement streamlining measures such as distribution cost recovery writers, purchased power capacity writers and formula rate plan. Another substantial aspect of utility growth plans are additional investments that are consistent with our obligations to maintain effective and efficient operations. In January, the Louisiana Public Service Commission approved the acquisition of 580-megawatt Acadia plant with cost recovery beginning immediately after purchase. With this final regulatory approval now in hand, closing is targeted by March 31. After the Acadia acquisition closing, four of the utility operating companies will have acquired five plants since 2005 to a well-developed, highly regulated and disciplined procurement process, the same we expect to use and continue to use going forward. On that point, utility operating companies continue to negotiate on potential acquisition of two gas-fired generation resources and an approximately 500-megawatt PPA proposal of a third-party supplier identified in the summer of 2009, long-term RFP that concluded last summer. While no definitive agreements have been reached today, we remain in active discussion, targeting conclusion at around the end of the first quarter. Regarding the Ninemile self-build project, a fourth resource selected with the RFP valuation process that was certified by the independent monitor, project development activities are ongoing with the definitive announcement estimated in the first half of 2011. This 550-megawatt combined cycle natural gas plant is targeted for completion no later than the summer of 2015. On a less positive note, Westinghouse has informed us that they will be unable to deliver Waterford 3's replacement steam generators for installation this spring as originally planned. After hydrostatic testing, which is the last step in the fabrication process, Westinghouse found separation of stainless steel cladding from the carbon steel base metal in the channel head on both replacement steam generators in areas beneath and adjacent to the divider plate. For those who do not have a Ph.D. in engineering, let's just say that would be a bad thing. Westinghouse continued its analysis to determine the root cause and develop repair options. Meanwhile, back at Entergy, spring 2011 refueling activities will include extensive inspections to validate preliminary engineering analysis that supports Waterford 3 operating safely for another full cycle before replacement of the steam generator. In transmission, the FERC approved in interim extension of the independent coordinator transmission arrangement in November 2010 and in certain enhancements to that arrangement in December 2010, providing for analysis of longer-term structures. Charles Rivers Associates has completed the cost/benefit analysis studies on the Entergy system showing the Southwest Power Pool, as well as Entergy's Arkansas joining the Southwest Power Pool on a standalone basis. They're expected to complete comparable cost/benefit analysis on the Entergy system or Entergy Arkansas standalone joining the Midwest ISO by the end of February. The results of these studies will be critical factors for retail regulators, including the Entergy Regional State Committee, or what we all call the ERSC, on evaluating alternatives for the current transmission structure. Under the procedural schedule established by the Arkansas Public Service Commission, Entergy Arkansas' assessment of its post-System Agreement strategic options is due in May. Last October, Charles Rivers and Associates' final report on the cost and benefit for the Entergy Arkansas joining SPP on a standalone basis found that the modest tower exchange of variable economic benefits were not sufficient to offset the fixed cost of Entergy Arkansas joining the SPP RTO. The Arkansas Public Service Commission has set a target date of October 7, 2011 for a final order on Entergy Arkansas' post-System Agreement structure. We need look no further than the most recent System Agreement issue to illustrate why their current agreement has been the source of so much dispute. An initial decision by the FERC ALJ issued last December found an increased accounting for wholesale opportunity Entergy sales violated the System Agreement and ordered refunds to utility operating companies. This case concerned the limited amount of short-term, wholesale energy sales, less than 0.5% of the total system to third parties from 2000 to 2009. In previous orders, the FERC rejected arguments that these sales were inconsistent with the System Agreement and that the other operating companies had a right of first refusal on these assets markets. Subsequent to the ALJ's initial decision, the FERC staff filed briefs on exceptions in January supporting the company's actual practices and consistent with utility operating company rationale, filed its own briefs. We continue to believe we and the FERC staff are on the right side of this issue, and given past practice and supporting FERC decisions and FERC staff positions, we were very surprised by the ALJ's initial decision. Turning to 2011, we have numerous goals at the utility, particularly with regard to the regulatory calendar. In addition to the annual formula rate plan filings in Louisiana, Mississippi and New Orleans, the utility will address potential timing in future rate filings and continue to pursue other regulatory mechanisms like riders and formula rate plans in Texas and Arkansas and the future regulatory processes and structures, plans for Louisiana and Entergy Louisiana, given that the FRP framework expires with the 2010 test year. Achieving resolution on long-standing issues regarding transmission structure and System Agreement is another aspiration. For this to happen in 2011, it will require parties to put the scars of numerous years of litigation behind them and focus on what is important now. There are numerous things that we believe that we can agree on, but achieving total agreement among the retail regulators on every issue is highly unlikely. But we clearly believe it is in everybody's best interest to come to a self-determined mutual agreement on as many of the issues that we can agree on as possible. Operationally, during 2011, the Utility will focus on managing major projects in its capital plan, consistent with cost and scheduled objectives, including plant fossil fuel, fossil generation acquisitions and the self-build CCGT plant, Nuclear's grand gulf upgrade and a revised plan to install the Waterford 3 replacement steam generators and ongoing transmission and generation of the projects. Completion of a majority of these projects is planned for 2012 and beyond. Regarding EWC's goals in 2011, EWC will continue to focus first and foremost on maintaining safe and secure operations for its generating fleet. But I can't emphasize enough the importance and the effort we put to resolving lingering uncertainties on license renewals. The NRC operating licenses expire next year not only at Vermont Yankee, but also at Pilgrim. While the prices and renewal process will extend beyond 2011, EWC will focus on encouraging the federal and state regulatory processes to move toward an expeditious conclusion. In addition, EWC will continue to execute on opportunistic but disciplined portfolio and risk management activities and transactions like the sale of the Harrison County power plant which closed on December 31, 2010. Before turning over to Leo, I want to recap a strong year of operational and financial accomplishments. Not only did we set another record for the sixth year in a row and 10 out of the last 11 years since 1999 for the highest consolidated operational earnings per share in company history, we also had the highest ever operating cash flow in company history. 2010 operational achievements are just as impressive. At the Utility, we achieved a number of constructive utility regulatory outcomes and improved customer service metrics across the board compared to 2009. At Nuclear, we delivered the highest utility fleet capability factor ever at 94.1%, completed two breaker-to-breaker runs at factory and at Vermont Yankee, set new plant records in consecutive operations at Fitzpatrick and Waterford 3, while Pilgrim and Cooper record runs continue today and recorded the highest plant production for a cycle at Indian Point 2 and for a refueling year at Palisades. 2010 ended with more than half of our nuclear plants evaluated in the excellent category as compared to its peers. Despite this, strong operational financial performance total shareholder returns for 2010 was negative. The overhang or uncertainties in New York and Vermont that I discussed earlier are certainly significant contributing factors. As is expected, depressed power prices compared to previous expectations of the market as evidenced by 2010 total shareholder return in which the bottom two quartiles in the Philadelphia Utility Index were dominated by the so-called hybrid or merchant generators. Having said that, we have to do a better job of driving the pace of favorably resolving the outstanding issues that we can influence, while continuing to enhance our market base point of view on power prices and expediting the execution of our hedging strategies, but maintaining the same discipline that we always have had in that regard. Just as we have not been waiting on operational regulatory issues to resolve themselves, we have not lessened our resolve on achieving the aspirations we have previously articulated. Despite going from leader to laggard on stock price growth, we believe we have made substantial progress in meeting our aspirations going forward. Utility is one of the fastest growing in the country. The EWC is one of the better hedge merchant generators relative to near-term commodity prices in a very uncertain market. Operationally, new records have been set in almost every aspect of the business. At the same time, our Board of Directors and management's commitment to seek and act on transactions that create value has not changed. The golden strategies I discussed today are the same ones we've talked about for a long time now. If at times it seems we have changed course or are saying something inconsistent with what we may have indicated on months earlier, it's only because we are a market-based point-of-view company, and that's how our strategies developed. Nobody knows better than you all that markets are dynamic. Given the realities and uncertainties of markets, a static point of view will inevitably lead to warehousing greater risk, lowering the probability of success and ultimately will endanger the financial viability of the firm. Options and optionality are good things, and we've strived to create and preserve them in the same way we think about generating free cash flow. In particular, in times of economic stress, if you have enough cash and have preserved your options, the future can look and can turn out very differently than if you're locked into a one dimensional course of action or strategy. You can rest assured we continue to refine our point of view everyday and to position the company with the flexibility and financial and operational strength so that we can and will execute on transactional opportunities at the appropriate time consistent with the realities of the marketplace. In regards to the Board, I am pleased to announce that former Senator Blanche Lincoln was elected to serve at the last meeting. She was one of the most respected members of Congress, and will bring immediate insight to the Board and management on virtually all the issues I discussed today. We will look forward to seeing you at the Analyst Conference in April, and we will continue to establish the groundwork for our strategies to capture opportunities for future success. Speaking at the analyst conference, we strongly encourage you to book your travel reservations now if you have not already done so, because all flights into or out of the city have sold out in past years for the Jazz & Heritage Festivals. We're in the planning stages now to make our conference the most informative and the most memorable event that we've ever hosted. And now I'll turn the call over to Leo.