Thanks, Paul, and good morning, everyone. Let's begin with Slide 8, which highlights the progress at our Skouries Copper Gold project. As of the end of Q3, overall progress on Phase 2 construction reached 73% and 86% when including Phase 1. We remain on track to achieve first copper gold concentrate production towards the end of the first quarter of 2026. With commercial production expected in mid-2026. We now have approximately 2,000 personnel on site, including 236 members of the Skouries operational team. This strong workforce has enabled us to derisk several areas early. Our skilled labor ramp-up began with concrete, structural and mechanical trades and is now transitioning to electrical, piping and control systems. While we've exceeded our labor targets, our focus remains on aligning skilled resources with active work fronts to support our execution plan. From a productivity standpoint, construction performance continues to track at or slightly above plan across the site. On the bottom of Slide 8, you'll see a photo of the open pit. This week, our fourth crew started operating, enabling the transition to a 24/7 rotation. As of the end of October, we had stockpiled approximately 531,000 tonnes of ore from the open pit and an additional approximately 93,000 tonnes from the underground, containing an estimated 21,000 ounces of gold and 5.5 million tonnes of copper, positioning us well as we prepare for commissioning and initial concentrate production. Turning to Slide 9. The photos here and on the following slides illustrate the steady advancement of work underway. Infrastructure around the process plant continues to progress. Final foundations for support buildings were completed in early October and structural mechanical piping and electrical work are ongoing across the key areas, including the substation, line plant, flotation blowers, compressors at guar area. The control building structure is complete with electrical installations underway on the first 2 levels. We have completed pre-commissioning of the concentrate filter presses and water testing of the flotation cells and tanks, preparation for pre-commissioning the pebble crusher are in progress. Moving to Slide 10. Progress continue on the thickeners, water testing of the first two thickeners is complete and piping installations have commenced following completion of the pipe rack installations. Slide 11 focuses on the filter tailings plant, which remain on the critical path. As of the end of October, structural steel installation at the filter tailings building was approximately 92% complete. The time lapse video showcasing this progress is linked for reference. Mechanical work progressed with the assembly of the filter presses with 4 complete at the end of the third quarter and the remaining tool on plan for completion in November with each press equipped with 98 plates. The compressor building steel structure is 98% complete and all 6 compressors and all -- and air receivers have been installed. As seen on Slide 12, construction of the crusher building structure is progressing. Concrete workers reached the final elevation above the foundation with the final wall lifts advancing. The primary crusher is assembled in position and work is underway on cable tray and internal structural steel stairways and platforms. Conveyor foundations between the primary crusher and the process plant, including the coarse ore stockpile are now complete. Conveyor preassembly and support steel installation are well underway. At the coarse ore stockpile on Slide 13, the stockpile dome foundation is nearing completion and assembly of the dome has commenced. The first of the 3 reclaim feeders and associated chute work has been installed with preassembly continuing on the remaining 2 feeders. Moving to Olympias on Slide 14. Third quarter gold production was 13,597 ounces and total cash costs were $1,869 per ounce sold. Production was impacted by flotation circuit stability issues earlier in the year, which led to a modification of the paste backfill blend to eliminate viscosity modifiers in the backfilled stopes. While plant operations recovered substantially in Q2, affected stockpile ore continued to be processed in the third quarter despite efforts to minimize negative impacts in the processing circuit, ongoing process water chemistry challenges further reduce the metal recovery during the quarter. While mitigation measures are underway, modest negative impacts on the metal recovery may persist as we continue processing material from affected backfill stopes and stockpiles. Progress continued on the planned mill expansion to 650,000 tonnes per annum during the quarter, with the early works advancing and demolition activities underway within the concentrator. All of the major equipment, including the verti-mill, flotation cells, thickeners, cyclones and E-room have been delivered. We expect progressive commissioning and ramp-up in the second half of 2026. We remain committed to driving transformation at Olympias. A comprehensive program is now underway to modernize and optimize the process plant and surrounding infrastructure alongside leadership and skills development program aimed at strengthening capabilities across all levels of the organization. I'll stop there and hand it over to Simon to discuss the Turkish and Canadian operations.