Louw Smith
Analyst · Scotiabank. Please go ahead
Thanks, Paul, and good morning. Starting on Slide 8 at our Skouries copper gold project. At the end of Q1, overall project progress was 66% for Phase 2 of construction. We continue to expect first gold production in the first quarter of 2026 and commercial production in mid-2026. We have experienced a steady ramp up of required skilled labor during the quarter with a heavy emphasis on concrete and filter plant mechanical and exceeded our target of 1,300 at the March, with approximately 1,375 personnel through the gate each day. While we have exceeded our current target, it's not just about the number of people on the ground, it's ensuring, we have the right skill sets and work fronts available, as we navigate and continue advancing the project. The plant construction productivity remains at or slightly better than our assumptions. On this slide, you can see on the top left photo, the concrete works advancing of the cause or stop power reclaim feet tunnel. The bottom photo shows the filter tailings building with a number of three feeder conveyors before installation. The top right photo shows the tank farm area at the filter tailings plant. Power cropping is complete and concrete placement has advanced with the first three of five tank bases having been completed. Moving on to Slide 9. During the first quarter the project capital invested at Skouries was $84 million. The spend in the first quarter was lower than Q4 2024, but in line with our expectations, as we had completed major procurement activities last year, including the tailings filter presses, major electrical equipment, and the process control system amongst other items. Over the coming quarters, we do expect to see increasing spend with higher procurement and construction spend in line with our expectations. We remain on track to meet our project capital guidance of $400 million to $450 million for the full year. In addition, we spent $6 million in accelerated operational capital towards the $80 million to $100 million expected this year. The spend included mobile equipment, that will be used as we move to owner operator miner in the open pit. Some of the equipment that we have received to date includes CAT777 trucks, and excavator, front-end loaders, graders and compactors. As we ramp up equipment and personnel on-site, we expect to see increasing spend over the next three quarters. Open pit mobile equipment is arriving on-site and being assembled and commissioned. Open pit grade control drilling is underway and we expect to start Phase 1 open pit mining during Q4 2025. The photos on the slide and the next few slides will show the advancement of the work underway. As you can see on the large photo on the left of the slide, infrastructure around the process plant continues to advance. Work in the process plant continues to expand to additional work fronts for mechanical installations and cable trays. Piping installations have started in the process plant and the pump house to enable the start of some pre-commissioning activities. In addition, water testing of the rougher flotation circuit is underway. Infrastructure on the west side of the main process plant building is shown, including construction works progressing on the secondary substation and control building. Cable play is completed in the substation and in progress in the control building. Infrastructure on the east side of the main process building as shown, including the structural steel installation is complete for the line plant and the blower's buildings. You can also see the progress of the installation of the conveyor that will transport ore from the cable crusher to the transfer tower. Moving to Slide 10. As you can see on the large photo on the right of the slide, the three thickeners continue to advance to plan. Concrete works for the first thickener has been completed and mechanical installations have commenced. The second thickener is approximately 85% complete and the third has its base completed. On the photo to the left, earlier this week, we reached an important milestone for the first part of the project. We have filled the tailings clarifier tank and started water testing in the tailings thickener circuit. Turning to Slide 11, at the filtered tailings building, we have included a link to an updated time lapse video showcasing the completion of the concrete foundation. Work has now transitioned to the installation of the structural steel and major mechanical equipment, both of which are advancing as planned. Piling for the compressor building is complete and piling for pipe racks and the clarifier area continues to progress. On Slide 12, work continues of the construction of the crusher building structure. The concrete foundation has been completed and work is advancing on the first level walls with approximately 60% of the walls completed in April. The first floor is expected to be finished in May, which will house the apron feeder to the course ore stockpile. Piling and drainage work for the primary crusher conveyor alignment to the course ore stockpile was completed and final excavations are well advanced. Moving to Olympias on Slide 13. First quarter gold production was 11,829 ounces and total cash costs were $2,398 per ounce sold. Gold production along with the production of byproducts was affected by unplanned maintenance for the pyrite concentrate filtration that we disclosed in Q4 and subsequently resolved in January. In addition, we encountered a challenge with flotation circuit stability. During the quarter, analysis has shown that, the flotation instability was generated by the viscosity modifier, that is added to the paste backfill to assist in paste pumping in the underground. The addition of this modifier impacted flotation circuit stability, impacted recoveries across all concentrates. Several mitigation steps have been enacted that have stabilized the flotation performance to date in the second quarter and production has recovered to expected levels in Q2. Total cash costs were impacted by lower product sales, lower gold sold and higher royalties, partially offset by slightly lower gold treatment and refining charges and slightly lower selling costs due to the lower volumes. I'll stop there and hand it over to Simon to discuss the Turkish and Canadian operations.