Paul Skayman
Analyst · JPMorgan. Your line is open
Thanks, Paul. Good morning, everyone. Today, I’d like to comment briefly on the operations for the first quarter of 2016. We produced nearly 141,000 ounces from our operations, including a small contribution from Olympias at 3,300 ounces. Generally, the operations performed reasonably well over the first quarter, mainly performing to budget with the exception of Tanjianshan, which had a slow start to the quarter due to low grade material being mined and removed from stockpile along with slightly low recoveries for this material. To start in Turkey, both Kisladag and Efemcukuru performed well during the quarter with 53,000 and 28,000 ounces, respectively, for the quarter. These were approximately in line with budgeted ounce production and lower cash costs than originally budgeted. Just as a reminder for Kisladag, first quarter is traditionally the slowest quarter, also the guidance for this year is lower than last year’s actual, and last year we were moving gold out of inventory compared to this year when we’ve effectively pulled it down already. In China, Q1 production totaled 58,000 ounces. As previously indicated, Tanjianshan had a slow quarter with lower grade material being treated, lower ounce production and higher costs. Jinfeng had a reasonable quarter doing better than budget on ounce production and costs. And White Mountain was solidly behind on tonnes, but ahead on cost for the quarter. Having said that, we still expect to maintain our original guidance for the year on these assets. On the development side, work continues on the construction of Olympias Phase II. At this stage, structural and mechanical disassembly is complete in the key areas, concrete demolition is well advanced. As Paul indicated, they expect to be commissioning early in 2017. As you’re all be aware, we received approval of the revised technical study just last week for the Skouries project. We would place the project in care and maintenance and used the first quarter of this year to wind down construction in place everything in a safe side. We’ll now work on putting elements of the team back to work to utilize the summer season for important earthworks and building construction. We’re working on updated schedules and capital cost estimates to complete by the open pit and underground places and we’ll have that available in the third quarter. As with any project, there are still some minor routine payments required to complete construction and we’re confident that these will be saved in a timely manner and will not further affect the schedule. Both Certej and Tocantinzinho, we continued with optimization studies during the quarter and at Eastern Dragon, we continue to work with the government on the conversion of the exploration license to the mining license. In March, we received formal notice of the application has been accepted and we’ll continue to update as things progress. During the quarter, we completed 7,500 meters of exploration drilling at the company’s operations and exploration projects in Rumania, Turkey, and China. In Rumania, drilling was conducted at the early stage project located about 20 kilometers northwest of Certej, testing outcropping alterations zones for potential epithermal gold mineralization. In Turkey, we continued testing the Kokarpinar target at the Efemcukuru mine and establishing the continuity of mineralized shoots in the vein system. And White Mountain in China, we completed underground drilling testing stepouts of the North and Far North ore zones encountering several high grade intersections. And with that, I’ll turn it over to Fabi.