Norman S. Pitcher
Analyst · CIBC. Please go ahead
Thanks, Paul and good morning everyone. I thought we’d do things a little differently this time and instead of sort of going through the numbers that you can find either in the operational results or the guidance we just released so I'm just going to sort of hit on what I see as the pertinent points for the various operations and development projects. Starting at Kisladag, very good year there in 2014, as we mined at the bottom of a mining phase that was above reserve grade, resulting in over 311,000 ounces of production for the year. As most of you are aware, 2015 production is lower and costs are higher, largely due to the reduced head grade, which is closer to reserve grade as we start in the next pit phase. We’ll put about 12.5 million tonnes of crushed ore on the leach pad this year and above 4.5 million tons of run of mine material. In terms of the expansion, we deferred that until 2017, which will allow us to complete Skouries and Olympias Phase II and we’ll see the benefit of expanding the crusher capacity to 20 million tonnes starting in 2018. In terms of reserves, we ended up with just over 8 million ounces. So when we account for depletion for mining in 2014. That’s about a 10% overall decrease in Kisladag, P&P. Efemcukuru, we had a good year at almost 100,000 ounces, looking at a similar year in 2015. Jinfeng also had a solid year as we got back into the bottom of the open pit, less ounces and somewhat higher cost in 2015 as we finish in the open pit and transition to primarily underground ore. Tanjianshan was our lowest cost producer in 2014; it looks like it will get the prize again for 2015. We started on the underground decline there to access the high grade QLT deeps deposit and expect to start underground drilling there in Q2 of this year. White Mountain benefited by higher grades in 2014, which were partly due to stope sequencing and partly due to positive grade reconciliation in some areas. Grade comes down closer to reserve grade in 2015, so it’s somewhat affecting the ounces produced. On a positive note, we did well with underground exploration at White Mountain and saw 20% increase in P&P reserves. At Olympias, as part of the Olympias Valley reclamation project, we continue to process tailings, treating just over 625,000 tonnes in 2014. At the end of 2014, there were just over 1 million tonnes of tailings left still to process. Stratoni, pretty regular year 2014 and 2015 as well, not much to comment there. Vila Nova Iron has been placed on care and maintenance; we did sell about 525,000 tonnes of iron ore in 2014. On the development side, as mentioned our development focus right now is Skouries and Olympias Phase II. At Skouries, engineering design work progress well and were over 80% complete at the end of the year. Pre-stripping in the open pit is ongoing and over 500,000 cubic meters were moved in 2014. Foundation for the SAG, ball and regrind mills were completed and mill installations are ongoing. We now have access to the base of the tailings dam and that would a focus for 2015. For Olympias Phase II, so for Phase II will be about 400,000 tonnes of ore for the underground mine with commissioning starting in mid-2016, capital spending over the next couple of years for that project will be about $30 million. Underground development work continues at Olympias, where we rehabbed over 900 meters of existing drifts and put in over 3,000 meters of new development and the Olympias decline is at the 1.6 kilometer mark, which is about 20% complete. As Paul mentioned, at Certej the full feasibility study will be released in Q2 of this year, we’re making good headway on that. On Eastern Dragon permitting is progressing well with excellent support from the Canadian government, the Project Permit Approval will be submitted this quarter and we expect approval in Q2. That timing will allow us to finish the additional steps required to restart construction during the summer field season. Last but not least on exploration, during 2014 we completed over 58,000 meters of exploration drilling at our mines and exploration projects, much of our in-mine resource drilling was focused at White Mountain. We also tested extensions to mineralized zones at Tanjianshan, within Kokarpinar, Efemcukuru and at Stratoni. Outside of our mines we drilled-tested five exploration projects in the Certej district in Romania, continued to define Piavitsa deposit in Greece and drilled three projects in Brazil. Our $40 million exploration budget for 2015 includes plans for over 68,000 meters of drilling, split roughly evenly between in-mine and Brownfields programs and earlier stage exploration programs. With that I will turn it over to Fabby.