George L. Kirkland
Analyst · ISI Group
Thank you, Jeanette. It's good to be back to discuss upstream performance and to provide an update on our operations. I'll begin by looking at our second quarter competitive position on earnings margins. So far this year, upstream margins were approximately $26 per barrel. Although not all our peers have announced second quarter results, we expect to continue to lead our competitors in this key metric. Based on the peers that have reported through the first half, we are almost $7 per barrel ahead of our nearest competitor. We have now held this top position for 12 consecutive quarters, reinforcing the quality of our investment decisions, the strength of our portfolio and the consistency of our performance. Next, let's look at returns. Our investments continue to deliver superior financial performance. For the second quarter, our return on capital employed was 25%. This, too, is expected to rank at the top of our peer group. Now I'll turn to 2012 production. Please turn to Slide 14. Our first half production averaged 2.63 million barrels a day at an average year-to-date Brent price of $114 per barrel. Based on the results to date, we are lagging the full year production guidance we gave you in January of 2.68 million barrels per day. There are 4 key drivers that will impact our full year production results. First, the Frade field has been shut in since mid-March. We are conducting an extensive technical evaluation of the area. Once all the technical evaluations are complete, partner support is in place and we obtain regulatory approvals, production is expected to restart and ramp up over time. Timing of the restart remains somewhat uncertain. Second, we have our first major turnaround at Tengiz SGI/SGP, and this is scheduled to start early in August and last for 6 weeks. The turnaround involves more than 6,000 workers. It includes normal inspections and repairs of equipment to maintain mechanical reliability and integrity. We will also take the opportunity to make improvements that are expected to slightly increase production capacity over the next few years. Next, we had commissioning delays at Angola LNG. We originally planned to start up in the second quarter. Commissioning activities are underway, and we've completed LNG berthing trials and LNG tankers are available for third-quarter cargoes. We are currently expecting the first cargo in September. Also influencing our production this year, and I mean in a positive way, are several MCPs that started up early relative to our plan. We have been pleased with their performance. Currently, we're performing at 98% of our initial guidance. And based on the items we just discussed, enough uncertainties remain so that I expect we will end the year slightly under our target. More importantly, our long-term guidance remains intact. Looking to 2017, we continue to expect production to grow to 3.3 million barrels per day at a Brent price of $79 per barrel. Now let's turn to Slide 15. We have an active year of exploration, and we plan to invest nearly $3 billion. The Gulf of Mexico is a key focus area for us where we continue to build our portfolio of prospects. During the recently sale, we were apparent high bidder on 15 deepwater blocks and 15 shelf blocks. We are currently drilling the Coronado well in the deepwater and the Lineham Creek well and ultra-deep Wilcox gas play on the Gulf of Mexico shelf. In another key focus area, Australia, we recently announced the Pontus-1 Carnavon Basin discovery, the fourth successful discovery out of the last 15 wells. We have several more exploratory wells to be drilled in Australia this year. We are also actively pursuing new test areas. One is South America, West Africa cretaceous play. We have an active drilling program in Liberia where we are on our second exploration well. And we recently acquired additional acreage in Suriname. We made a new entry in the Kurdistan Region of Iraq. This acreage is in the appraisal and exploration phases, which is consistent with our strategy of seeking early opportunities. We are also progressing our unconventional portfolio. We have drilling activities in the U.S., both in the Permian Basin and the Marcellus, the Canadian Duvernay, Poland, Argentina and China. In the Ukraine, we were awarded a tender that gives us the right to negotiate a production-sharing contract for 1.6 million acres. This acreage is on trend with our Poland and Romania acreage. Next, we'll talk about our progress on major capital projects. Please turn to Slide 16. We continue to see good performance from our first quarter start-ups, Usan, Tahiti 2 and Caesar/Tonga. In the second quarter, we achieved start-up of Agbami 2. We have brought online 1 new producer and 1 water injection well. Our plan includes 10 wells in total, 6 of which are producers. We reached a Final Investment Decision to expand our Bibiyana natural gas field in Bangladesh, where we have a 98% interest. This new project will include expansion of the gas plant to process increased gas volumes from the Bibiyana field, additional development wells and an enhanced condensate recovery unit. The project is expected to boost Chevron's total natural gas production capacity in Bangladesh by more than 300 million cubic feet per day to 1.4 billion cubic feet per day. Our start-up is expected in 2014. We entered front engineering and design for the Rosebank Project in the U.K. This is our first operated development in the west of Shetlands basin. This field holds significant potential with estimated total potential recoverable oil equivalent resources of 240 million barrels. Turning to Slide 17, I'd like to give you an update on our Australia LNG projects. Let's start with Wheatstone. We made a Final Investment Decision on Wheatstone last September. We have achieved our key milestones for the year. We have completed the pioneer camp with 100 beds and continue work on phase one of the fly camp, which will add an additional 500 beds. We currently have about 300 workers on site. Just this month, we cut first deal on the platform top sides in the DSME fabrication yard in South Korea. We now have long-term contracts in place for over 80% of our equity LNG volumes. The remaining activities for 2012 focus on detailed design and preparing for plant site works to commence in the fourth quarter of this year. To date, approximately $15 billion in contracts have been awarded including more than $7 billion in local Australian contracts. The contracts are a mix of lump sum, reimbursable time and material and unit rate. During the quarter, we signed a non-binding Heads of Agreement with Tohoku for LNG offtake. We also executed an equity Sales and Purchase Agreement with TEPCO, bringing Chevron's interest in the offshore platform and facilities downstream of the platform to 64% and our interest in the upstream permits to 80%. We do not intend to farm down any further. With this sale, Chevron's net capital investment is expected to be about $20 billion. We're in the process of obtaining final government approvals of this sale. Now let's turn to Gorgon. Please turn to Slide 18. Gorgon achieved FID in September 2009 and is now over 45% complete. We're making good progress on our 2012 milestones. In June, the first 4 pipe rack modules arrived on Barrow Island. In July, construction began on the domestic pipeline. Next month, the first plant equipment module is expected to arrive. And later in the year, we expect to start installation of the Train 1 compressors. I'd like to update you also on a few areas -- additional areas of progress. Through design optimizations, we have upgraded the nameplate capacity of the individual trains to 5.2 million tons per annum for a total of 15.6 million tons. This is a 4% increase in capacity. Fabrication and delivery of modules are on track. We have completed 2 of the 3 main berths at the material offloading facility, allowing efficient simultaneous offloading of modules and other construction materials. Two LNG tanks are under construction, and we've completed all 14 ring sections of the first tank. The roof is now structurally complete and is ready to be floated into its final position. This strong progress on the tanks has taken them off the critical path, which is unusual for an LNG project. We have drilled 8 of the 18 development wells, 7 in Gorgon and 1 in Jansz, and we're pleased with the sub-surface results we're seeing. Progress on the upstream facilities and subsea pipelines are on plan. We posted several photos of our progress at Gorgon on the web page, chevron.com. You will see links on the home page and Investor page called Gorgon progress photos. I encourage you to check in occasionally, as we will periodically update Gorgon project pictures. Moving to Slide 19. We've received many questions about Gorgon cost. We want to be responsive as we can and provide the insights we can with the information we have to date. As you are aware, the project was sanctioned in 2009 at USD 37 billion and at the current exchange rate at the time of USD 0.86 to the Australian dollar. The stacked bars chart shows the budgeted cost at FID and how they were broken down, 30% upstream and 70% downstream. We have now awarded more than $28 billion in contracts with more than half to local contractors. The contracts include a mix of lump sum, unit rate and reimbursable time and material. The contract mix will change over time as contracts are completed and/or converted. Procurement and fabrication, along with the upstream component, are mostly non-Australian-dollar-based. These are the top 2 seconds on the stacked bar. The other component shown on the bar chart are primarily Australian-dollar-based. Overall, about half of the total costs are in Australian dollars. Procurement and fabrication and the upstream components are on plan in terms of both cost and schedule. Regarding logistics, the 5% component, we have 3 primary supply bases. Activities at the Dampier and Perth supply bases are meeting or exceeding plan. However, the Australian Marine Complex at Henderson, which handles transshipment of larger cargo, has not been as productive. To mitigate, we are streamlining our logistics processes and have added additional resources. We have a strong focus on insuring critical materials arrive in sequence and on time to support construction activities. Looking at the construction and labor segment, we have experienced some delays due to weather. We are still in the early stages of our on-island activity, and we'll need several months on Barrow Island to assess labor productivity. Remember that by design, the project is modularized to limit on-island activities. We've also seen Australian labor costs trending higher. This could impact both construction and management services. Because there are a number of variables in play, we currently have a detailed cost review underway. We're evaluating our performance to date and incorporating new information to update our expectations for the remainder of the project. Over the next few months, our assessments will help us gauge movements in costs, which we expect to provide towards the end of the year. I would like to emphasize that our view of the Gorgon project has only been enhanced since FID. I remain very confident in the economics and the value created by this project. While we are seeing cost pressures, in large part associated with a 20% strengthening of the Australian dollar, it's important to note that oil prices, which determine the project's revenue stream, are about 60% higher than at the time of project sanction. Further, the development well results to date are encouraging, which has greatly reduced the reservoir uncertainty. We've increased the capacity of the foundation project by 4%, and we continue having success with our exploration program, providing us with confidence that we will have additional gas volumes to support further expansions at Gorgon. With that, I'd like to turn it over to Pat.