The Jeffersonville, Indiana factory, as you mentioned, is in the middle of the building construction and also the equipment. We already shipped in the Phase -- most of the Phase 1 equipment, and those Phase I equipment, which is about 2 gigawatt of capacity, solar cell capacity, those equipment stay in a warehouse in Indiana right now waiting for the building to complete. So I think Phase 1 of about 2 gigawatt, the Jeffersonville facility, we have announced a proposal, a plan to reach 5 gigawatt, and we cut into Phase 1 and Phase 2. So we are quite conservative when it comes to actually spending money. So, at this moment, phase one, as I said, equipment are almost there. So, we will -- I think we will complete the Phase 1. Well, and the Phase 2 decision will probably be made in the summer or after summer, the final decision. And so I hope, I think this budget reconciliation will come to a conclusion, final form, either before the summer or after summer. So, in a way that we are not spending a lot of money on the Jeffersonville, other than what we already committed. And so the schedule is in parallel with the schedule of this budget reconciliation process. So, if somehow -- we think the final language will be reasonable. Final language about FEOC will be reasonable. And but also as you said, we are ready to change the capital structure once the policy is clear, the language is clear, the legal explanation is clear, then we will make our existing capacity to meet with the whatever the new language. But we don't want to completely stop. So we are still continuing with, design some final like detailed design of the factory, and also certain civil construction work. Because the IRA itself only have a few years of shelf time, right, even the previous original IRA already contains a phase down after 2030. And I think by 2035, right, all the ITC and also the advanced manufacturing quality, the so-called 45X will stop. So that's only a final time -- so only finite amount of time, limited amount of time. So, if we delay too much, the project will become uneconomic. So, we'll balance this and we're spending some money to keep the construction and design work going and however, for most of the equipment other than what we already shipped in, will probably only be able to make decision, let's say, in August or September. I hope by that time, this budget reconciliation is already completed.