Thanks, Damian. Turning now to our Palm Valley drilling program. As shown on the slide, we are halfway through a 2-well program that could restore Palm Valley production to the plant capacity of around 14 terajoules per day. Achieving this target would increase Central's total gas production by around 40%. The first well, Palm Valley 14, has been successfully drilled to a measured depth of 2,942 meters, but encountered a water-bearing fracture or fractures close to this depth. Three bridge plugs were then set to isolate these fractures with the last being set at 2,729 meters. A subsequent short duration test measured gas flow of approximately 3.2 terajoules per day and indicated initial gas production of around 3 to 4 terajoules per day once tied into the existing network. This indicative result is below expectation and the initial rates achieved from recent Palm Valley wells. However, a short-duration rig test is not necessarily a reliable indicator of long-term production performance. At this time, Palm Valley 14's ultimate performance remains uncertain, but we will get a clear picture once the well is commissioned and producing through the surface facilities. It is worth noting here that the Palm Valley gas production depends almost entirely on intersecting natural fractures, which vary considerably in number, width and length across the field. Some of the larger fractures, which extend to great depths, may act as a conduit for formation water, which can constrain or prevent gas production at any stage of the well's life. None of these factors can be fully assessed from a short-duration rig-based flow test, which is why we need to wait for results from a steady-state production. By way of comparison, the PV12 well, completed in July 2022, initially encountered water when drilled. But after setting isolation plug, well cleaned up and has now been producing reliably for over 4 years. Despite the risks and uncertainties, drilling at Palm Valley remains an attractive investment. Existing spare plant capacity means the marginal cost of additional production is low. Importantly, for Central, bringing new Palm Valley gas into the Northern Territory market via PV14 and PV15 before year-end allowed us to secure a long-term gas sale agreement with the Northern Territory government and that will underpin our forward cash flows through 2034. To put Palm Valley 14 into context, in an initial flow rate of 4 terajoules per day, assuming a typical Palm Valley decline rate would provide a payback on the current forecast well cost in around 3 years and recover almost half of that cost by the end of next year. With some Palm Valley wells producing for more than 10 years, this well can still deliver attractive economics even at these lower initial production rates. Well has now been completed and tie-in activities are underway with commissioning expected before the end of October. Once PV14 is online, we will have a much clear view of its production potential. The rig has now moved to PV15, which we expect to spud over the next few days. Importantly, we do not believe that PV14 results change the risk profile for PV15. PV15 is located approximately 3 kilometers away and targets the Southern Flank of field rather than the Northern Flank, which was targeted by PV14. It is also closer to the crest of the structure, and further up-dip from possible water sources. PV15 will be only the second well after the successful PV12 well to directly access the Southern Flank. We remain confident that a good result from PV15 would still achieve our target of restoring Palm Valley sales capacity to its plant capacity of approximately 14 terajoules per day. Turning now to our broader growth portfolio. Over the past year, we have taken deliberate steps to diversify Central beyond our existing Amadeus Basin operations and established positions in 2 proven Australian petroleum provinces, the onshore Otway Basin in Victoria and the Cooper Basin in South Australia. We hold a 20% interest in PEP 169 in the Otway and a 49% interest in PEL 677 and 24 associated retention leases in the Cooper. The attraction of these areas is straightforward. Both basins have a long history of successful petroleum production, extensive technical data and established infrastructure. This provides us with potentially lower cost exploration opportunities; and in the event of success, shorter and more direct routes to market. We currently have 3 exploration wells planned across these 2 basins in 2027, subject to joint approval, obviously. These wells will give Central exposure to both gas and oil opportunities while also providing access to the larger and higher-value Southern and East Coast markets. It's important evolution in our portfolio. We retain the cash-generating strength and near-field upside of our Northern Territory assets while adding exploration opportunities in established basins where success could materially increase our reserves, diversify our revenue and create the next phase of growth. I'll now look at each of these new basin positions in more detail. One near-term growth opportunity is the Enterprise North prospect, where well is planned for 2027, subject to joint venture approval. Enterprise North is located approximately 2.5 kilometers up-dip from and along the interpreted spill path of the producing Enterprise gas field. It is also supported by seismic amplitude anomalies, which provide additional technical support ahead of drilling. The primary target is the Waarre C Formation, a well-established and highly productive reservoir in this part of the Otway Basin. Nearby discoveries have demonstrated permeability above 1,000 millidarcies with Enterprise 1 flowing at more than 50 terajoules per day during testing. Just as importantly, the prospect is close to existing pipelines and the Iona, Otway and Athena gas processing facilities. That infrastructure provides potential routes to the Victorian gas market without a significant capital expenditure usually required to create entirely new development corridors. Enterprise North is targeting up to 79 billion cubic feet of gas in place, of which approximately 16 billion cubic feet would be attributable to Central's 20% interest. These volumes are prospective and unrisked and drilling is required to determine whether a recoverable accumulation exists. Nevertheless, success at Enterprise North could roughly double Central's annual equity gas production and provide a material new source of gas close to an important domestic market. Another near-term growth opportunity is the Cooper Basin. Cooper is one of Australia's most established petroleum provinces with a long history of oil and gas discoveries and an extensive network of pipelines, processing facilities and oil export infrastructure. Our acreage was relatively underexplored during its suspension between 2016 and 2025, but it benefits from extensive existing seismic coverage. Earlier this year, a significant amount of this seismic data was reprocessed and reinterpreted to support re-ranking of these various reservoir targets. The JV has previously identified 17 prospects and leads across the acreage with at least 7 considered close to drill ready, subject to completion of this target selection review. The JV is now finalizing plans to drill 2 exploration wells in 2027, subject to joint venture approval. The initial program is expected to focus on the Birkhead oil and Patchawarra gas targets, both are proven Cooper Basin plays and provide additional diversification in basins and commodities. The existing infrastructure in proximity to our Cooper assets is a significant advantage. In the event of success, oil can potentially be transported using established trucking and export arrangements, while gas may have access to existing pipeline networks. This can reduce the capital and time required to commercialize the discovery. The Cooper position, therefore, complements our assets in the Amadeus Basin, it introduces exposure to potential oil reserves and global liquids markets while retaining gas upside in the basin with well-established routes to market. It is a disciplined entry into a proven region with multiple follow-up opportunities if the initial wells are successful. Bringing all these activities together, we have a busy program ahead of us. As I covered on Palm Valley, PV14 tie-in is underway and commissioning expected in the next couple of weeks. PV15 will follow as a second well in the campaign, and we hope to have it online by the end of the year. Together, the wells are targeting total Palm Valley sales capacity to approximately 14 terajoules per day on a 100% joint venture basis, although actual production will depend on individual well performance and natural field decline. We are currently producing about 5.5 terajoules per day at Palm Valley, so we need initial production of around 9 TJs per day in aggregate from PV14 and PV15 to achieve that. During 2027 and subject to joint venture approval, we are planning to drill the Enterprise North exploration well in the Otway Basin and 2 exploration wells in the Cooper Basin. As I mentioned, these provide material gas and oil upside with established routes to key markets. Beyond that, the growth program includes the potential drilling of a sub-salt well at Mt Kitty in early 2028, again, subject to joint venture approval. This prospect provides potential exposure to helium, hydrogen and natural gas in the Amadeus Basin. We are continuing to seek farm-in partners for Mt Kitty in order to mitigate our cost and risk exposure. Importantly, all of these growth activities are supported by a strong financial base. The repayment of the gas overlift position has released more than $7 million of annual cash flow, while new multiyear contracts provide improved revenue visibility. Central enters these programs more financially resilient with a diversified exploration portfolio and a potential series of near-term drilling catalysts. That wraps up the formal presentation. So at this point, we are happy to answer any questions that have been submitted online. Thanks.