Scott Perry
Analyst · David Haughton, CIBC
Okay. Thank you, John, and good morning, ladies and gentlemen. Thanks for joining our conference call. I'm just starting off on Slide 4 of the presentation deck that John referenced. Just speaking to each of these highlights. First - just firstly most importantly, in terms of safety. Our mine sites, our operations had another safe quarter, and we continue to roll out phase two of our company-wide safety leadership program called Work Safe - Home Safe. The key objective of this program is as best possible, fostering an environment of zero harm in the workplace. One of the key safety highlights during the quarter was at Öksüt. Oksut is now in construction and the project is 26% complete. But what is most pleasing is we've now just recently achieved a key milestone of 750,000 hours of lost time incident free construction activities. On December 10, we expect that we'll be at 1 million hours of lost time incident free operations. So a key milestone, and just want to extend my congratulations to our operations team there at Öksüt. Construction activity continued at the Öksüt project throughout the quarter. The main access road and the side road construction were substantially completed and the installations, including the crusher area, the ADR plant area, the heap leach pad site and other site infrastructure are advancing safely and according to plan. During the quarter at Mount Milligan, mill throughput averaged 40,805 tonnes per calendar day or approximately 55,000 tonnes per operating day. Throughout the quarter, throughput was impacted at Mount Milligan by lower than forecasted chemical availability related to an unscheduled shutdown in mid-July for repair work at the primary crusher and another unscheduled shutdown at the end of August and into early September to repair transformer damage from a lightning strike. The scheduled shutdown in late September was also extended to replace the SAG mill shell liners. The company submitted an application on October 18 to enable drawing of water from Philip Lake, Rainbow Creek and additional groundwater sources within a radius of approximately six kilometers of the tailings storage facility. The company is still in discussions with regulators, First Nations and other affected stakeholders regarding these applications and expect that access to these sources may be granted as early as the end of January 2019. Such approvals would apply until the summer of 2021, enabling the company to benefit from the spring melt flows for three seasons while a long-term updated water supply plan is developed. Just referencing Kemess. The Kemess project achieved another milestone in the quarter as it received its effluent discharge permit after receiving the amendment to its Mines Act Permit in the second quarter, which ultimately approved the underground mine plan and the corresponding reclamation program for the Kemess Underground Project. Just moving into the operations and our production results. During the quarter and earlier than planned, Kumtor accessed and started mining and processing the higher-grade material from the SB zone in the central pit. As a result, the company has increased its production guidance at Kumtor for this year to a new increased range of 490,000 to 510,000 ounces. Likewise, our company-wide production has increased to 665,000 to 705,000 ounces. Given the growing levels of gold output, we have also lowered our expected all-in sustaining costs on a by-product basis. At Kumtor, our all-in sustaining cost guidance has been reduced to $700 to $750 per ounce. And likewise, at Mount Milligan, we have also reduced our all-in sustaining cost guidance with the new guidance being $825 to $875 per ounce. All of these favorable reductions bring the company-wide consolidated all-in sustaining cost guidance down to our new range of $782 to $829 per ounce sold. Just in terms of the earnings, in Q3, we achieved net earnings of $6 million or approximately $0.02 per share. In terms of the quarterly production, the operations produced a total of 181,000 ounces of gold and 20 - 12.7 million pounds of copper in the quarter. And I think what was really impressive was the very low all-in sustaining cost at which this production was produced. Our company-wide all-in sustaining cost during the quarter was $698 per ounce bringing the year-to-date to $861 per ounce. Financially, the business delivered approximately $67.1 million of consolidated cash from operations before changes in working capital. Kumtor and Mount Milligan generated $64 million and $19 million, respectively, before working capital changes. Lastly, we finished the quarter with $545 million of total liquidity. And after the end of the quarter, we announced the sale of our Mongolian business unit for net proceeds of $35 million. Moving on to Slide 5. Slide 5 just contains four charts that just graphically illustrate some of the key financial highlights during the quarter. In the top left, you can see the waterfall chart that's illustrating our year-to-date cash flow profile. As I mentioned, Mount Milligan and Kumtor were both positive free cash flow generation during Q3. And as we make our way now to Q4, now that Kumtor has accessed the higher grade SB zone, we're expecting robust gold production at continued low operating cost, and we should see increased free cash flow generation and profitability. The liquidity chart in the top right just our liquidity profile at the end of Q3. As I mentioned earlier, we've got approximately $545 million in liquidity. So very well-funded. And moving forward, our business plan is an internally funded business plan. In the bottom left is just our net debt position. Finished the quarter with net debt of approximately $142 million. So just in terms of our overall indebtedness or the leverage through the business, it's very low. And then lastly, just in terms of the profitability. The retained earnings chart in the bottom right. We finished the quarter with an excess of $1.1 billion of retained earnings on the balance sheet. Just moving on to the next slide on Slide 6. Slide 6 just highlights each of our individual operations and future development projects, and we're just referencing this against the World Gold industry all-in sustaining cost curve. As you can see, our existing operating assets, we've been very close to being lower cost quartile at the company-wide guidance. I think what we're all very excited about is what is going to represent our third source of high quality low cost production, being the Öksüt project in Turkey, which is now construction. It's just going to favorably complement our existing low cost profile and will be an important third source of low-cost production. Just moving on to Slide 7. Really, the key bullet points I'd highlight here is the third bullet point. Obviously, Kumtor had a very successful year-to-date in terms of their mine productivities and just how they're ultimately phasing and sequencing the mine. They are ahead of plan. As I've mentioned a couple of times, they're now into the high-grade SB zone, and that's really going to underpin the robust gold production result this year. As a result, we've increased our gold production guidance at Kumtor to 490,000 to 510,000 ounces for this year. This resulting increase in gold output is going to have a favorable reduction in terms of Kumtor's all-in sustaining cost profile. We've actually reduced the guidance there to a new range of $700 to $750 per ounce. So the fourth bullet point is worth highlighting. The Öksüt Project continues to progress very well. We're now at 26% completion, and the project is progressing on time and on budget. And as I mentioned, it's incident free, very safe construction, which is great to see. In terms of the table at the bottom, in terms of the quarterly result, just really want to highlight the low all-in sustaining cost profile at each of our operations. Kumtor had a fantastic quarter, producing its gold as low as $662 per ounce. Likewise, at Mount Milligan, it was very low cost during the quarter at $677 per ounce. And then you can see in the last row in the table there, on a company-wide basis, we came in at $698 per ounce. And again, it is this level of performance that's underpinning the favorable reduction in our guidance in terms of all-in sustaining cost. Our new guidance on a company-wide basis, calendar year 2018 is all-in sustaining cost of $782 to $829 per ounce. Just moving on to the next Slide on Slide 8. Some of the bullet points I'd highlight. The second bullet point with regard to Mount Milligan. During the quarter, we did operate at 55,000 tonnes per operating days, which was good to see. The next bullet point below in terms of our gold and copper recovery efficiencies, we continue to improve year-over-year, which is something we've been targeting. So that's great to see as well. And in terms of the fourth bullet point here, one of the key items that we have been focusing on is accessing - getting approvals for additional access to water. We submitted our applications to - after the end of the quarter, and we're expecting to have additional access to water from Philip Lake, Rainbow Creek and groundwater that's within six kilometers of the existing tailings storage facility. We think when this application is granted, it will provide significant volumes of water with the onset of the 2019 spring melting season. The last bullet point that I reference, and the final bullet point there, which is we're reconfirming our annual production guidance for Mount Milligan both in terms of gold and copper and again, we are favorably reducing the all-in sustaining cost guidance. Just moving on to Slide 9. Öksüt obviously represents our next producing gold mine coming through the construction pipeline. As I mentioned, we're 26% complete on this and the project is on time, on budget and we're targeting first gold pour in Q1 of 2020. What we put together here is just a few images of some of the construction activities that are taking place. On the top left there, you can see the mine access road. Moving in a clockwise direction, you can see the construction activities of the main crusher area. Top right is the primary crusher facility. In the bottom right is our electrical substation. In the middle center of the bottom is our ADR plant construction area. And the very bottom left of the slide is our secondary crusher facility. Everything seems to be going really well here in terms of the progress. And again, we're hoping to be able to demonstrate an on-time, on-budget construction on what is going to be a very important third source of profitable production for Centerra. With that, I'm going to pass this slide over to Darren Millman, our Chief Financial Officer. And Darren will walk us through some of the financial results.