Mick Routledge
Analyst · Scotiabank
Thank you, Aoife. Before getting to the quarterly review, I want to add that the development and training programs Mitch touched on earlier have had a clear impact on our ability to effectively grow our people, align objectives and establish a safe working environment from the ground up. Slide 19 highlights the continuation of our multiyear downward trend in injury rates. And I strongly believe this investment in our people is a big reason for that success. Excellence in health safety and environmental performance is the foundation of a world-class business. Looking back on Coeur’s first half of 2022 from an operational perspective, our teams have worked hard to overcome considerable headwinds on costs and global supply chain disruptions. When we factor in the addition of a major expansion project, at one of our four operations or performance is even more impressive. Our priority in the second half of the year is on maintaining that momentum by: first, steadily advancing POA 11 and carefully managing Rochester’s transition; second, implementing business improvement initiatives that drive efficiency and productivity at our operations; and third, and most importantly, focusing on safety and wellbeing of our people. Turning to our second quarter production summary on Slide 6 and beginning with Palmarejo, metallurgical recoveries improved due to ongoing blending optimization, and metals grid remained consistent. We are confident in our ability to achieve production targets for the year. We have a good handle on unit costs at Palmarejo guidance has been adjusted largely to reflect an expected change in the allocation of costs on a core product basis. Moving to Rochester, gold and silver production benefited from strong ore placement rates in the first quarter. Gold ounces produced increased 37% quarter-over-quarter while silver ounces produced increased 5%. Tons placed in the second quarter were impacted by the installation of the pre-screen pilot system, which was completed on July 22. Ramp up of the pre-screen pilot system as well as optimization of the product size placed on the leach is now underway. These learnings should help us further de-risk and optimize POA 11 as we move forward with our pre-screen system. Following a slower first half of the year, we remain confident that Rochester is on-track to achieve 2022 production guidance for gold and silver. COGS guidance for 2022 has been revised upwards to reflect higher diesel, labor and maintenance cost. As a general matter, we anticipate period of elevated costs throughout Rochester’s transition period, as experience is gained and best practices are developed. These learnings we believe will ultimately lead to a major reversal on costs of the scale and efficiencies in an expanded operation are fully realized. Being with Rochester and the POA 11 expansion for a moment, Mitch hit the key Q2 highlights. On July 29, the transmission lane and onsite substation was successfully energized by Nevada Energy, as another example of the tangible progress taking place. In the second half of the year, we will see the pace of activity continue, with the start of the product conveyor installation along the crusher corridor roof set of secondary conveyors, commencement of pre-screen installation and the completion of the metal Coeur electrical systems among many others. The mining and project teams are aligned and working well together with over 1 million hours without a lost time injury, zero on the project to date. At quarter end, the project's estimated cost remained approximately $600 million, roughly $523 million of the project capital has been committed and we incurred $350 million of that estimated total through the end of the second quarter. Key Q3 updates on the final engineering and procurement of the pre-screen along with an updated multicolor analysis of the contingency will be completed as part of our ongoing governance over the project. This work is not yet complete, but it is fair to say, we continue to see some inflationary pressures and could see the final cost of the project end up around 5% higher than the current estimate. Switching over to Kensington. Production increased on the back of Kensington's highest ever quarterly throughput, driven by improved mining and mill efficiencies. The team continues to catch up on delayed stock development due to COVID impacts on the workforce in the first quarter, and we remain optimistic that Kensington is on-track to achieve the 2022 production guidance. Wrapping up with Wharf, we continue to place higher grade material, which led to a 15% increase in gold production versus the first quarter. Wharf remains on track to achieve its 2022 production guidance range. 2022 gold cost guidance has been revised upwards to reflect high anticipated diesel costs. With that, I'll pass the call over to Tom.