William Lytle
Analyst · Jefferies
All right. Thanks, Mike. I just got back from the Goose, so I may be a little Ferrell during this, so bear with me. As Mike said, on the three operations, we expect to meet or exceed all of our targets for the year, but probably what everyone wants to talk about is Goose. So just going back to what has been completed there. Goose, all the major construction activities, which required -- were nearly completed at the end of the quarter, and the mine ramp-up is now well underway. The focus for the third quarter now turns actually to optimizing the current operations and increasing the throughput to full capacity. As Mike indicated, a ramp-up to commercial production is expected in September 2025. Things which were completed in the first half of 2025 at the Goose include the completion of the mining of the Echo pit. Remember, that was our tailings facility and commissioning. So we are now placing tails in Echo. Full ramp-up of mining of the Umwelt open pit in the second quarter. We also had continued development of the Umwelt underground. We completed the Fresh Air Raise 1 already and in the process of developing Fresh Air Raise 2, which will be needed in the second half of 2025. We commenced dewatering of the Llama pit. All these things are required to run the mill correctly. This provides freshwater and reclaim water to the mill. We developed the Umwelt open pit and underground, and that remains a priority to ensure that the adequate mill feed volumes are maintained. If you look at around the other operations, Mali continued its strong performance for 2025, exceeding gold production expectations again in the second quarter. As Mike said, cash costs per ounce were also lower than expected. Underground after meeting with the government last quarter -- last month, the underground production has commenced as announced on July 30. The underground development is well advanced with over 9,300 meters of development work plus the installation of all required underground mining infrastructure, having all been performed prior to commencing production. If you remember, we were actually given a permit to do all the development. So even though we were 30 days late on the starting of mining of ore, we, in fact, continue to develop right up until July 30. So the question I've heard or being asked several times is whether or not we think we're going to get the ounces required from underground, we absolutely see a path to make sure that all the required ounces from underground will be delivered in 2025. The regional project, we continued with our meeting with them. We continue to work with the state of Mali to finalize the approval of the regional exploitation permit in the third quarter of 2025, just kind of late breaking. We've actually had our first technical session with them this morning. We absolutely see a path towards getting this permit. B2Gold is ready to commence pre-stripping activities with the Fekola regional infrastructure. Remember -- once again, this was one of those facilities where they allowed us to do all of the infrastructure development. So the haul road is in place and all the infrastructure is already in place. We're just waiting on a permit to start pre-stripping. Subsequent to June 30, 2025, the Fekola mill celebrated a significant milestone with 4 million ounces of gold produced since the inception of the project. At Masbate, the operations continue to perform well with a world-class safety track record, which I think we announced more than 2,400 days without a lost time incident. Mine production significantly outperformed expectation, and we anticipate consistent production in the second half will result in strong 2025 performance and robust margins. Otjikoto is also going very well. The open pit and underground went well during the second quarter with production also exceeding expectations. During the second quarter, remember, we're working on this Antelope deposit. So we continue to focus on developing that with a target release in the third quarter of 2025. And then the other development project is Gramalote. We released the positive feasibility study. Work has commenced on the modification of the work plan and environmental impact study, and we expect to be complete in late 2025 or early 2026. We anticipate that the permit modification time frame should be approximately 12 to 18 months. With that, Clive, I'll turn it back over to you.