Great. It's through. I trust that everyone can see that. And Emma, if you're happy, I'll just jump into the presentation. So what you're seeing in front of you is -- sorry, on the heading slide is just the site present -- the site celebration that we had with the Minister of Mines last week to celebrate our FID. And I thought it was a really good slide to start because I know this is post quarter, but as you can see from all the happy faces there, this was an extremely important occasion for us and celebrated in style both the Mining Minister and the Commissioner of Mines. Right. In terms of the quarter and the reason why we're so pleased is you often have a plan. But when a plan comes together, it always really makes things feel just that much better. So what we managed to achieve this quarter is, first and foremost, is we completed the CNOL strategic investment, which was worth $320 million. And on the back of that as well, we also had a successful AUD 124 million institutional equity placement. The combination of these has been what has been behind our FID decision. I think you'll remember, we've always said that the FID decision for Bannerman has really been around making sure that we understand how we're going to fund the project all the way through to production. And the combination of the deal and the successful fundraise is what's allowed us to make the FID decision. We have a very strong liquidity position as at the end of September. Bannerman itself has AUD 175 million approximately in the bank, but that excludes the cash that sits in the Etango JV and other investments. And then obviously, the Etango JV cash balance is USD 295 million, but that also excludes additional cash that is currently being held in the Namibian subsidiaries. Also, obviously, on site, as you know, I was extremely excited around what is happening on site, but I'm being very pleased to see that we're still tracking on budget and schedule in terms of our early works program. And then I think another pleasing thing has been that the long-term price for uranium has stuck consistently at $97. And that obviously is a positive for the industry moving forward, even though I do believe it's going to move even higher. So post quarter and the end of the highlights, I did touch on that a little bit earlier, but really the positive FID, which was taken on the basis of the Etango design. We allowed a plus or minus 10% CapEx estimate, and we're still forecasting 3.5 million pounds with first production in 2028. Another highlight for us as well was the appointment of Danie van Aswegen. So Danie has been in the mining industry in Southern Africa for a number of years. Originally, he working on the platinum mines in South Africa, both underground and as a project manager and then moving across to Debmarine, where he had an expert position and also ran projects and development work for Debmarine. Danie has been with us for a while now and originally joined as a COO, and we are really pleased to announce his promotion to CEO of Bannerman Mining Resources. He has a strong technical background, a strong project background, but most importantly, Danie is a people person that loves to make points by telling stories. And this really has managed to pull the team together on the back of the change from one MD to another. And we're very, very, very happy with the results and the decision to appoint Danie. And then obviously, the culmination of that was a celebration with Honorable Modestus Amutse, Namibia's Minister of Industries, Mines and Energy, who came out to site, did a visit, joined the ceremony and the flag raising ceremony. So the Etango flag has now been raised on the mine, and we will continue to deliver Etango as we have been doing to date. And we are now 100% ready for full-scale construction. I've just got a couple of slides following this, which show where we were at the end of September. And as you can see, these are the bulk earthworks, which are now 99% complete. And what you're looking at there are the solution dams for the pregnant liquor. This one here was the first structure that we started on the site, which is the primary crusher. And as you can see, the actual structure for the crusher is now completed and the earthworks wall, which creates the access berm behind the crusher is progressing at reasonable speed and is currently tracking on schedule. We've also completed the ore stockpile tunnel, which sits underneath the stockpile. And what you're looking at here to give you an idea of the size, that's the exit for the conveyor as it comes out from underneath the stockpile, and those are the wing walls to ensure that the stockpile doesn't start falling on to the conveyor. And the fine ore silo is moving ahead in line with schedule. And as you can see, starting to get significantly higher. It still has a couple more raises to go, but we should have this completed in early New Year. And then the secondary and tertiary crushing facility, we are one concrete pour away from the point where we'll start installing our structural steel work, and we're very pleased once again with both the quality and the progress on this building. And then the permanent water supply line has also been a really positive local contractor once again, installing the pumps and the pipeline from the main supplier at the Swakopmund NamWater facility heading towards the mine. And what we did have post quarter as well is we actually did the bridge installation as well. And that's effectively the quarter in a summary. As you can see, there's an awful lot that has happened in the quarter, but we are extremely pleased to see the way the team has pulled together to achieve these results. And I'm more than happy at this point, Emma, to take any questions.