Michael Garcia
Analyst · Cormark Securities
Thank you, Mike. Good morning and thank you for joining us to discuss our fiscal second results. As always, I will begin my remarks by addressing what truly matters most to us. The safety of all out employees. At Algoma we believe in safety without compromise and continued dedication has led to a significant improvement in our loss time injury frequency rate over the past decade. Furthermore, we bring the same focus and attention to safety as we continue progressing on the largest capital project in our history our EAF Transformation Project.I want to commend the team for working 420,000 hours with no loss time injuries to date and want to emphasize the importance of safety, especially as we enter the winter months. We will continue to work diligently as we relentlessly pursue our goal of achieving zero workplace injuries. Next, I'll cover key events and milestones during our fiscal second quarter and subsequent to its end. As well as update you on the progress of our transformative EAF project.I will then turn the call over to Rajat for a deeper dive into the numbers and the discussion of our strong liquidity and balance sheet before closing with an update on market conditions. Our results for the fiscal second quarter of 2024 were in line with our previously disclosed guidance for both shipments and adjusted EBITDA.These results reflect solid operational performance against a challenging backdrop in steel markets, where the recently resolved UAW strike at various US auto making facilities impacted demand and pricing. During the quarter, we continued progress on phase II of our plate mill modernization project. Including commissioning and testing of the inline shear. We expect the shear to be online later this month and to wrap up plate production through the end of the year.This higher production level will allow us to capture market opportunities and to build inventory ahead planned outages for the implementation of the final phase of the modernization project. The project team has worked through the detailed implementation steps and identified opportunities to further de-risk this phase. Originally, we had planned on one outage standing 40 days.However, we have identified advantages to splitting the outages into two shorter duration outages of up to 20 days, which we expect will mitigate the impact on our customer base while also reducing commissioning risk. The first outage will be in April of next year and the second outage will be scheduled for later in the calendar year to align with our planned maintenance outages providing further advantages. We still expect increase in production volume over the course of the year with much less impact on our customers. Turning to other strategic initiatives.We have made significant progress on securing key raw material inputs during the quarter. We signed a two-year extension to our existing iron ore purchase contract with U.S. Steel with an option for a third year at our sole discretion.By extending the existing contract, we now anticipate our iron ore volumes needed to make the transition to electric arc furnace steel making are fully covered giving us certainty of supply and uninterrupted access. On the coking coal front, we have settled our calendar 2024 contract needs and pricing for this raw material is expected to be down low double digits in 2024.So given the certainty of labor, due to the 5 year union agreement signed last year, the contract for our iron ore needs for the next few years and our coking coal contracts for calendar 2024 we have solidified our inputs and created better visibility into our cost structure for the next several quarters, positioning us to expand margins especially as steel price has continued to improve from recent strike impacted weakness.We are optimistic as forward prices have hovered around $1000 U.S. per ton for hot rolled coil in recent days, reflective of the pent up demand and low inventory levels at certain customers. Next, I'd like to update you on our progress during the quarter on our transformational EAF project. This will still will ultimately increase our throughput capacity by roughly a third, from 2.8 million tons per year of liquid steelmaking capacity by conventional means today to 3.7 million tons, employing dual EAF furnaces upon completion.The higher output will match our expanded downstream finishing capacity as we increase throughput at our plate mill. Importantly, this will improve overall product mix while simultaneously lowering our carbon emissions by approximately 70% when fully operational.When factoring in the makeup of our power supply when we switch to EAF operations, we expect to be one of the greenest producers of steel in North America.During the quarter, cumulative investment in the EAF project reached $456 million or 54% of our expected total project cost at the midpoint of our project budget.We have made meaningful progress since quarter end securing uncontracted portions of expected project cost, and as of today, approximately 80% of the total project budget is under contract.We expect to contract the remainder that as of the project budget by the end of March 2024. Furthermore, it is important to point out that as of now, only 5% of the total contracted amount is subject to time and material adjustments, meaning the vast majority is under fixed price terms.This demonstrates significant de-risking of the EAF project over the past several months as we progress towards the startup commissioning in late calendar 2024.As a reminder, our startup plan continues to include normal production from our existing steel making facility, while ramping up steel production from our EAFs in calendar 2025. Followed by a complete switch to EAF production.I spoke earlier about our successful efforts to secure coal and iron ore inputs for our existing operations and when you think about the inputs for EAF steelmaking, one of the most important is power.As we mentioned previously, we already have the required power to run the electric arc furnaces at our current run rate of 2.2 million to 2.4 million tons of shipments without relying on the blast furnace, utilizing on-site power generation and the current grid.We can utilize hot metal from the blast furnace opportunistically which would provide further upside to our current capacity. In this quarter, we received a system impact assessment for the second phase of our project, which means when the local 230K Volt line installed, we can run either EAF unit without running our on-site power plant.Also subsequent to the quarter end, the Ontario government's announcement and issuance of an order in council to accelerate regional power infrastructure upgrades provides further assurance for our long-term power requirements for our EAF project. All-in-all a significant amount of progress has been made substantially de-risking the availability and cost of the power needed for new EAFs. It’s an exciting time in Sault Ste Marieas our existing facilities operate normally and work on the EAF accelerates. I would like to once again thank all of our employees whose execution continues to deliver solid operational and financial results safely while simultaneously driving the EAF project forward.Now I will pass the call over to Rajatto go over our financial results for the quarter and give more details on the expected funding of our capital expenditures.