Richard Thomas
Analyst · Canaccord Genuity. Please go ahead
Thanks Neil. Moving on to Slide number four. In the first half of 2024, we processed relatively low-grade material at Segovia, averaging at 9.2 grams per ton, and we did experience an unplanned seven-day plant maintenance shutdown in April, which affected our H1 production for the year. However, since May, the Segovia plant has been operating at its design capacity of 2,000 tons per day, and is on track for expansion to 3,000 tons per day by early 2025, to support our future production growth. Despite these operational challenges in the first half of the year, Aris Mining remains on track to meet the low end of its full year production guidance of 220,000 to 240,000 ounces. And what gives us confidence is this, that we have opened up some very high-grade sections in the El Silencio mine, which we identified in our drilling program, and we are currently exploiting these. We are seeing this grade reporting to the world at present. Also, we have managed to upgrade our Bolivia shaft, and that production has been increased by 25%, which allows us increased production from the El Silencio mine. Moving on to Slide number five, where we provide further details of the cost structure of our Segovia operations, and our contract mine partners' business model. In quarter two, 2024, the cash cost per ounce is $1,222 per ounce for mine operations, and $1,174 per ounce for untitled CMP operations. Cash costs for owner mining remained relatively stable, with a modest 3% increase compared to quarter one, 2024. However, the cash costs for untitled CMPs rose by 11% of the previous quarter, directly driven by a 12% increase in realized gold prices, to $2,308 per ounce in Q2. Similarly, the purchase and processing costs per ounce for material delivered by third-party CMPs who operate off-title increased by 29% in quarter two. This was due to both the rise in realized gold prices and the delivery of significantly higher-grade material in Q2, which averaged 29.1 grams per ton, compared to the 18.7 in the previous quarter. However, despite the higher costs third-party CMP monthly purchases contributed approximately $7.2 million to Segovia's all-encompassing margin of $60.6 million in the first half of the year, while consuming only 5% of Segovia's milling capacity. Moving on to Slide number six, the Segovia process plant expansion progressed as scheduled, with overall engineering work 85% complete. The manufacturing of the new bore was completed on time, and final payment has been made. The new bore is expected to be delivered on-site in September. Construction progress also includes the installation of concrete retaining walls, material receiving bins, foundation equipment, and CMP receiving facilities, and the assembly of conveyor belts and other capital equipment. Additional work on the foundations and capital expenditures have increased the overall budget to $15 million, as previously discussed in our press release on 16 July. The Segovia processing plant expansion is complete in early 2025, following a ramp-up period, Segovia is expected to be able to produce over 300,000 ounces of gold per year. As Neil mentioned in our 2024 exploration program, which is approximately 70% complete, has delivered excellent results as it's closed in our press release on Monday. We expect to report updated mineral resources and reserve estimates for Segovia in quarter four. Moving on to Slide 7, I'd also like to update you on the construction progress at Marmato Lower Mine. As you know, we commenced construction of the new Marmato Lower Mine in Q3 2022, following the receipt of environmental permits in July 2023. The lower mine will access wider porphyry type mineralization below the upper mine, with both mines estimated to produce combined 162,000 ounces of gold per year over a 20-year mine life. Detailed design and engineering of the process facility are over 90% complete. Manufacturing of the process product equipment, ordered in Q1 of this year, is progressing on schedule, with long lead items on track to meet contractual delivery dates. The portal development is ahead of schedule, with completion expected by the end of the month. The contractor selected for the [indiscernible] town is preparing equipment for demobilization, and key items like the drill rigs are already on site. Preparation for the road access to the processing plant is progressing well, and asphalting has commenced this month. Design and engineering of the power supply to the mine and process plant are complete, and the land rights acquisition process continues to remain power line. Design of the paste plant and water treatment plant are well underway. As of the end of July 2024, the estimated cost to complete the lower mine construction was $246 million of which $122 million will be funded by stream financing, resulting in $124 million of cost to complete on a net basis. Finally, I'd like to draw your attention to the video link at the bottom of the slide, which I recommend you visit for photographs and video updates of the Marmato lower mine construction progress. With that, I'd like to hand over to our CFO, Richard Orazietti.